I thought it a good time to write about the Powersite North Sanitary Sewer Improvements Project as it's been a couple of years since my last post on this riveting topic. First off, it turns out that getting all those easements done may have taken the
Great River Associates a bit longer than they anticipated.
An excerpt taken from their
webpage provided me with a clue:
- When will
construction start?
“The construction of the project
will be bid once the design is complete, a Missouri Department of Natural
Resources Permit is obtained, and necessary easements and property have been acquired.
At this time, it is expected that the project will be bid in late 2011. The
biggest variable in determining this time is the easement and property acquisition
phase of the project. Construction is expected to commence within 60 to
90 days after bidding.”
Uh, that was like two years ago! In
addition, a recent newspaper article which was published on February 1, 2013 in
the
Branson
TriLakes News indicated they were only ‘
roughly 30% through the easement
process’! (At that rate, one has to wonder if this project, which started in
2008, will see completion prior to the end of the current decade). Out of curiosity, I did try
checking the calendar they used to maintain on their site, but that too has been
removed!
So, when I recently received paperwork in the mail asking me
to sign over my land rights to the GRA so they could establish both a temporary construction
and permanent easements, I already had a few questions. For one thing, after inspecting a aerial map they sent me, I took note of
the fact that the placement of the property lines appear to lie over and
occlude the same land easements that the Corps of Engineers maintain. Did they
get an easement signed that covered this Federal easement? I don’t know.
Another question that arose in my mind concerns the sewer line branch
that enters my property. After looking at the aerial map they sent, it appears to
be 20 feet off to the west of where it should be to put it in line with the
sewer connection to the house! Now, while I’m certainly no engineer - that just
seems wrong somehow.
Finally, and justifiably so, other residents that live on
the same street as myself are wondering what will happen when this group begins
trenching. To my uneducated eye, it appears as though they plan to dig
somewhere along the road that goes in front of my house. On one side exists a
water utility easement and on the other are power lines. So, where is that trench
going to go? (As a side note, it would be great if they could replace the aging
water delivery infrastructure while they're doing all this).
Like I said, I have a lot of questions as do most of the
neighbors I’ve talked with. To that end, I called Shawn Berry the Project Manager at (417) 886-7171 to take them up
on their promise to come out
an meet me to help answer all my questions. I did note that they would prefer to
meet with each homeowner on an ‘individual’ basis. I'm looking forward to a re-post after this meeting takes place!