Tuesday, July 24, 2018

Bull Shoals Roundabout drive bys!




Aug 13, 2018 8:55 AM

Since the video cam which was recording traffic conditions at the Bull Shoals Bridge Project was yanked by MODOT recently, I thought I'd start doing a series of simulated commute runs to let others see what was going on... I planned to add one of these whenever conditions change significantly. At the time of this post, the crews were still working on asphalting the approaches to the new bridge. Traffic was flowing normally also.

August 14, 2018

MODOT Press release:

One-Lane Traffic ?Round the Clock
At Route 76/Bull Shoals Bridge Further Delayed until Aug. 20
 
Forsyth Area, Taney County – Drivers can expect one-lane traffic with temporary traffic signals regulating traffic on Route 76 at the Bull Shoals Lake bridge project east of Forsyth starting Monday, August 20, the Missouri Department of Transportation said.

The move to the temporary traffic pattern during this phase of the bridge project has been further delayed due to weather.

Originally, the plan called for Route 76 to be closed for up to two weeks to connect the new bridge into the existing highway. However, after hearing strong concerns from the community about the closing of the Route 76, MoDOT committed to work with its project contractor to minimize the impacts to the traveling public. MoDOT and the contractor developed an approach to keep traffic flowing during this part of the project.

It’s expected the one-lane traffic and temporary traffic signals will remain in place for up to two weeks.

Mid-way through the process of building the new pavement connection, Route 76 traffic will move to the new bridge. However, one-lane traffic and the temporary traffic signals will remain in place until all the connecting pavement is complete.

Drivers can expect delays on Route 76 during this phase of the project. They are urged to allow plenty of extra travel time and expect backups on Route 76 approaching the bridge.
During the work, law enforcement officers will assist with traffic control during busy traffic times. Contractor crews along with law enforcement will assist first responders through the work zone during emergencies.

ADDITIONAL INFORMATION: Construction is scheduled to begin the week of August 13 on the new roundabout at the intersection of Route 160 and Route 76 at the north end of the new bridge. Drivers can expect lane closings at times with crews and equipment close to traffic. 





.